Connection Process

  • Surveying the area and obtaining the energy requirement of the customer through Demand Assessment Sheet (DAS). Signing of Gas Sales Agreement with customer and collecting connection charges and desposits.
  • Completion of upstream work upto customer premises (Meter location). Customer to complete downstream work from metering unit to usage point.
  • Collecting required documents before commissioning from customer towards downstream work as listed below:
  1. Internal Piping Test Certificates.
  2. Test Certificates of all fittings (valves/pressure gauges/regulators, etc.).
  3. Third Party Pressure Testing Certificate for internal piping work.
  4. Internal Piping Layout Diagram showing all fittings upto final user point inside the customer premises.
  5. A copy of letter informing Health and Safety Directorate with piping layout diagram inside the premises.
  6. A letter by customer indemnifying IMC Limited against any kind of loss in case of leakage in internal piping.